COVID & Lockdown Projects

Quarantine Centre

Getting work done during a regular working environment is never a challenge.

However with the whole of India being under lock-down and extended lock-downs, even the emergency services were short staffed. Medical facilities were already stressed and flooded with a continuous  influx of patients. The nation came together and Gujarat Enterprise managed to get a real estate project ready as part of their contribution to assist with medical infrastructure during this pandemic.

However the facility could not be commissioned due to electric meters not being installed. The lock-down only added to delay in execution of  this noble gesture,

We were approached to sort out this issue

On analyzing the issue and discussions with various internal and external teams,
we set a target to complete this assignment  on an emergency basis

On-time Project Completion

  • Understanding the deliverable from all stakeholders
  • Rescheduling inspection schedules with regulatory authorities
  • Budget apportionment
  • Liaisoning with the senior technicians and Management at Adani Electricity & MCGM
  • Continuous followup
  • Onsite presence during key visit to handle any emergency
  • Electric Meters installed
  • Project Completed as per client’s satisfaction.
  • Project handover for a Quarantine  Center.